GUIDE TO SHIP REPAIR
ESTIMATES
(IN MAN-HOURS)
GUIDE TO SHIP REPAIR
ESTIMATES
(IN MAN-HOURS)
Don Butler
OXFORD AUCKLAND BOSTON JOHANNESBURG MELBOURNE NEW DELHI
Butterworth-Heinemann
Linacre House, Jordan Hill, Oxford OX2 8DP
225 Wildwood Avenue, Woburn, MA 01801-2041
A division of Reed Educational and Professional Publishing Ltd
A member of the Reed Elsevier plc group
First published 2000
© Don Butler 2000
All rights reserved. No part of this publication
may be reproduced in any material form (including
photocopying or storing in any medium by electronic
means and whether or not transiently or incidentally
to some other use of this publication) without the
written permission of the copyright holder except
in accordance with the provisions of the Copyright,
Designs and Patents Act 1988 or under the terms of a
licence issued by the Copyright Licensing Agency Ltd,
90 Tottenham Court Road, London, England W1P 9HE.
Applications for the copyright holder’s written permission
to reproduce any part of this publication should be addressed
to the publishers
British Library Cataloguing in Publication Data
A catalogue record for this book is available from the British Library
Library of Congress Cataloguing in Publication Data
A catalogue record for this book is available from the Library of Congress
ISBN 0 7506 4834 1
Typeset by Avocet Typeset, Brill, Aylesbury, Bucks
Printed and bound in Great Britain by Biddles Ltd,
Guildford and King’s Lynn
Contents
List of figures vii
List of tables ix
1 Introduction 1
2 Drydocking works 5
Berth preparation 5
Docking and undocking 6
Dock rent per day 6
Hull preparation 8
Hull painting 10
Rudder works 13
Propeller works 14
Tailshaft works 17
Anodes 20
Sea chests 22
Docking plugs 22
Valves 23
Fenders 25
Anchors and cables 26
Chain lockers 27
Staging 28
3 Steel works 29
4 Pipe works 35
Contents v
5 Mechanical works 41
Overhauling diesel engines (single-acting, slow-running,
two-stroke, cross-head) 42
Overhauling diesel engines (single-acting, slow-running,
in-line, four-stroke, trunk) 47
Valves 52
Condensers 55
Heat exchangers 56
Turbines 57
Compressors 60
Receivers 61
Pumps 62
Boilers (main and auxiliary) 67
6 Electrical works 69
7 General works 83
8 Planning charts 85
Sample graph loadings for major trades in ship repairing 89
Index 93
vi Contents
Figures
1 A vessel sitting on keel blocks undergoing repairs in
dry dock 6
2 A small grab dredger in a graving dock 8
3 Hull preparation by water blasting and hull painting by
airless spray 10
4 The rudder and propeller of a small vessel in dry dock 15
5 A propeller undergoing tests 16
6 Repair of damage to shell plating 31
7 Main engine cooling-water pipes 37
8 A main propulsion diesel engine 42
9 A ship’s medium-speed main engine 47
10 A ballast system valve chest 53
11 A standard screw-lift globe valve 54
12 A vertical electric-driven centrifugal water pump 63
13 A main electrical switchboard in a machinery control room 69
14 A generator control panel in a main switchboard 70
15 A standard AC induction electrical motor 72
16 A ship’s main diesel-driven AC alternator 74
17 Grouping of electric cables on a cable tray 78
18 Control panels of a ship’s auxiliary equipment 81
Figures vii
Tables
2.1 Shifting of blocks after docking vessel 5
2.2 Dock services 7
2.3 Removal of rudder and stock for survey 13
2.4 Propeller works (fixed pitch) – 1 13
2.5 Propeller works (fixed pitch) – 2 15
2.6 Propeller polishing in situ (fixed pitch) 16
2.7 Tailshaft/sterntube clearances 17
2.8 Removal of tailshaft for survey 18
2.9 Gland and Simplex-type seal 19
2.10 Anodes on hull and in sea chests 20
2.11 Sea chests and strainers 21
2.12 Sea valves 23
2.13 Ship side storm valves 24
2.14 Hollow fenders in half schedule 80 steel pipe 25
2.15 Anchor cables (per side) 26
2.16 Chain lockers (per side) 27
2.17 Erection of tubular steel scaffolding 28
3.1 Steel works renewals 32
4.1 Pipe work renewals in schedule 40 and schedule 80
seamless steel 35
4.2 Pipe clamps 38
4.3 Spool pieces 39
5.1 Top overhaul 43
5.2 Cylinder liners – 1 44
5.3 Bearing survey – 1 45
5.4 Crankshaft deflections – 1 45
Tables ix
5.5 Four-stroke trunk-type main engines 48
5.6 Cylinder liners – 2 49
5.7 Bearing survey – 2 50
5.8 Crankshaft deflections – 2 51
5.9 Overhauling valves 52
5.10 Main condenser 55
5.11 Overhauling heat exchanger 56
5.12 Main steam turbines 57
5.13 Flexible coupling 57
5.14 Auxiliary steam turbines 58
5.15 Water-tube boiler feed pumps (multi-stage type) 59
5.16 Oil tanker cargo pumps 60
5.17 Air compressor (two-stage type) 60
5.18 Air receivers 61
5.19 Horizontal centrifugal-type pumps 62
5.20 Reciprocating-type pumps, steam driven 64
5.21 Reciprocating-type pumps, electric motor driven 64
5.22 Gear-type pumps (helical and tooth) 65
5.23 Stearing gear 66
5.24 Cleaning of water-tube boilers 67
6.1 Insulation resistance test 69
6.2 Switchboard 70
6.3 Electric motors 71
6.4 Electric motors for winch/windlass/crane 72
6.5 Electric generators 73
6.6 Installations of unarmoured, flexible, multi-core,
rubber-insulated cable 75
6.7 Installations of rubber-insulated, armoured flexible cable 77
6.8 Installations of rubber-insulated, armoured flexible
single-core cable 79
6.9 Installations of electric cable tray 80
6.10 Installations of electric cable conduit 82
7.1 General cleaning 83
7.2 Tank cleaning 84
7.3 Tank testing 84
x Tables
1 Introduction
This guide has been produced in order to outline to technical superintendents
of ship owners and ship managers the manner in which the
commercial departments of ship repairers compile quotations. The
ship repairers use their tariffs for standard jobs to build up their quotations.
This guide is based on these tariffs, but is made up in manhours
to assist long-term pricing. It can also be of assistance to
shipyards without this information to prepare man-hour planning
charts, helping them to assess manpower requirements for jobs and
to produce time-based plans. Man-hours have been used so that this
book will not be ‘dated’ and can be used without encountering the
problems of increases in costs over the years. Where man-hour costs
are not possible, these have been noted and suggestions made to
compile costs against these items.
Apart from steel works and pipe works, no cost of materials has
been included within this book. Only man-hours are used in order
that the compiler may assess shipyards’ charges based on the current
market price of labour.
Where materials are conventionally supplied by the repair contractor,
these have been built into the labour costs and evaluated as
man-hours. Apart from steel works and pipe works, the cost of materials
in the jobs listed are generally minimal when compared with
labour costs. So, apart from these two, most of the other costs will be
consumables.
A comparison between various countries has been included. The
workers of some countries have more efficient skills than others.
Some establishments have more sophisticated equipment than others.
Introduction 1
However, common ground has been assumed in the output of
workers in standard jobs.
It is stressed that this book considers only ship ‘repairs’, that is,
removing damaged, worn, or corroded items, making or supplying
new parts to the pattern of the old and installing. It is not meant to be
used in its entirety for new building work, although, in some areas, it
may prove useful.
Unless specifically mentioned, all the repairs are in situ. For
removing a specific item ashore to the workshops, consideration
should be given to any removals necessary to facilitate transportation
through the ship and to the shore workshop and the later refitting of
these removals, and an appropriate charge made.
In calculating the labour man-hours, it should be borne in mind
that these will vary for similar jobs carried out under different conditions,
such as world location, working conditions, environment,
type of labour, availability of back-up labour, etc.
The labour times given in this book are based upon the use of
trained and skilled personnel, working in reasonable conditions in an
environment of a good-quality ship repair yard with all necessary
tools, equipment and readily available materials and consumables.
All these factors should be considered when calculating the
man-hours and if conditions vary from that of the assumption of this
book then factors should be applied to compensate for any shortfall
in any conditions. As an example, if the work is being carried out in
a country which suffers from heat and high humidity, then the output
of a worker can fall to 50% that of the same worker in another
country which has an easier working climate.
With reduced work outputs for whatever reason, a ship repair
yard will need to mark up their pricing rates according to their type
of variance, and this is passed on to the ship owner. The estimator
should consider influences applicable and may need to apply a factor
to increase the man-hours according to whatever may reduce the
output of a contractor’s workers.
Once the man-hours have been calculated, the estimator must
then apply a pricing rate to the total. These vary from place to place
and should be ascertained from the ship repair establishments under
consideration. The variance of the rates will be applicable to certain
considerations which can be applied. These considerations can
include the local economy, how hungry the yard is for work, the
2 Guide to Ship Repair Estimates (in Man-hours)
current workload of the yard and other similar situations. The estimator
can look at the economic climate of the repair yards and ascertain
a variance factor for each yard and apply these accordingly.
The figures shown in this book are not to be viewed as invariable.
Obviously different shipyards have different working conditions
and techniques, so the man-hours for the work can vary.
However, the figures shown can be used as a fair assessment of the
work in general and can produce price estimates for budget purposes
to a shipowner. This is the object of the book.
When requesting quotations from shipyards the quotes received
always vary considerably. The figures given in this book reflect competitive
tariff rates.
The author has long-term experience in the ship repair world
and he is currently a director of a marine consultancy. He is a former
sea-going engineer, qualified and experienced in steam and motor
ships, even with experience of steam reciprocating engines and saturated
steam fire tube boilers, rising from there to repair superintendent.
He has extensive ship repair yard experience gained from production,
commercial and general managerial positions.
Seeing a lack of this type of publication, the author decided to
put his long-term experience to use in order to assist those responsible
for compiling repair specifications with a pricing strategy so
they may build up costings for their planned repair periods.
Included in the text are a number of tips to be applied in the
preparation of repair specifications and finalizing contracts with ship
repair yards.
Introduction 3
Drydocking works 5
2 Drydocking works
Berth preparation
This item is included within the charges for docking and undocking
and should also include for dismantling and removal of any specially
prepared blocks.
Table 2.1 Shifting of blocks after docking vessel
This covers shifting of blocks at the request of the owner for access
works not known at the time of quoting. This involves cutting out the
soft wood capping of the block, shifting the block and reinstalling at
a different location.
Man-hours
DWT Keel block Side block
< 20,000 5 3
20,000–100,000 10 5
100,000–200,000 16 8
> 200,000 20 12
6 Guide to Ship Repair Estimates (in Man-hours)
Docking and undocking
This is variable dependent upon world location and market demands.
Dry docking charges regularly change depending upon the economic
climate, so an owner’s superintendent should check with selected
drydock owners for their current rates.
Dock rent per day
The above comments also apply here.
Figure 1 A vessel sitting on keel blocks undergoing repairs in dry
dock
Drydocking works 7
Table 2.2 Dock services
Man-hours
Service <100 LOA >100 LOA
Fire and Safety watchman per day 8/shift 8/shift
Garbage skip per day 2 4
Electrical shore power connection and
disconnection 4 5
Electrical shore power per unit Variable Variable
Temporary connection of fire main to ship’s
system 5 6
Maintaining pressure to ship’s fire main per day 3 3
Sea circulating water connection 3 4
Sea circulating water per day 4 4
Telephone connection on board ship 3 3
Supply of ballast water per connection 6 8
Supply of fresh water per connection 3 5
Connection and disconnection of compressed
air 3 5
Gas-free testing per test/visit and issue of gasfree
certificate 8 10
Electric heating lamps per connection. 4 5
Ventilation fans and portable ducting each 5 5
Wharfage: charges to lie vessel alongside Variable Variable
contractor’s berth. Usually a fixed rate per
metre of vessel’s length.
Cranage: charges variable, dependent
upon size of crane. Variable Variable
Notes:
Contractors often charge for temporary lights provided for their own use in
order to carry out repairs. This is an arguable point as it is for their benefit
and not the owners. It should be classed as an overhead and costed accordingly.
Provided there are none of the ship’s staff utilizing the temporary lights,
then it should be a contractor’s cost.
8 Guide to Ship Repair Estimates (in Man-hours)
Hull preparation
● Hand scraping normal
● Hand scraping hard
● Degreasing before preparation works
● High pressure jetwash (up to 3000 p.s.i.)
● Water blast
● Vacuum dry blast
● Dry blast (Dependent upon world location. Prohibited in some
countries)
● Grit sweep
● Grit blast to Sa 2
● Grit blast to Sa 2.5
● Spot blast to Sa 2.5
● Hose down with fresh water after dry blast
● Disc preparation to St2
The charges for hull preparation works should be given in price per
square metre. This will enable the owner’s superintendent to calculate
the price for the full scope of works.
Figure 2 A small grab dredger in a graving dock
Special notes for hull preparation
The ship owner’s superintendent should be fully aware of the manner
in which the ship repair yard has quoted for the hull preparation
works. This is to obviate surprise items when confronted with the
final invoice.
A ship repair yard should quote fully inclusive rates, which
cover the supply of all workers, equipment, machines, tools, and
consumables to carry out the quoted works and also for all final
cleaning-up operations. Inflated invoices have been known from ship
yards covering the removal of used blasting grit, removed sea
growth, etc. The dry dock may not belong to the repair contractor and
additional charges may be made by the dry dock owner for these
items. Ensure that these charges are well highlighted before acceptance
of the quotation. It is far better to clear up these matters prior to
the arrival of the vessel instead of being involved in arguments just
before the vessel sails. Time taken to consider what a yard may see
as justifiable extras before the event is well spent prior to placing the
order, when everyone in the yard is eager to secure the contract.
The use of dry blasting grit is being phased out in certain areas
as it is environmentally unfriendly. Dry sand is not used for similar
reasons and is also a health hazard. The choice is for vacuum dry
blasting or water blasting using very high pressures. Water blasting
can use fresh or salt water, but the salt water must be followed by
high-pressure jetwashing using fresh water to remove the salts.
Drydocking works 9
10 Guide to Ship Repair Estimates (in Man-hours)
Hull painting
● Flat bottom
● Vertical sides
● Topsides
● Touch up after spot blast
● Names, homeport, load lines, draft marks.
The charges for hull painting works should be given in price per
square metre, and a fixed rate for names and marks. This will enable
the owner’s superintendent to calculate the full price for the scope of
Figure 3 Hull preparation by water blasting and hull painting by
airless spray
works. (See below for the method of determining the painting areas
of ships’ hulls.)
Notes for hull painting
Shipyard standard rates will apply for paints considered as ‘normal’.
This refers to paints being applied by airless spray method up to a
maximum of 100 microns (μ) dry film thickness (dft) and having a
drying time between applications not exceeding 4 hours. The owner
should ensure that the shipyard is aware of any special, or nonconventional,
painting compositions which may be used.
Additional note on the supply of painting
compositions
It is generally accepted practice for all painting compositions to be
owner’s supply. This is due to the paint manufacturer giving their
guarantee to the purchaser of their paints. Included from the manufacturer,
within the price of the paints, is their technical back-up, provision
of a technical specification on the preparation works and paint
application, and the provision of a technical supervisor to oversee the
whole process of the paint application. If the paints have been applied
to the satisfaction of the technical representative, then the full guarantee
will be given to the purchaser by the paint manufacturer.
The contractor is only responsible for the preparation works and
the application of the painting compositions. Provided they have satisfied
the conditions of the technical specification, and the attending
technical representative, then there will be no comeback on them if
a problem with the paints occurs at a later date.
With the owner being the purchaser, the paint manufacturer will
have the responsibility to provide new paint in the event of problems.
The application is the responsibility of the owner. He will have to
bear the cost of drydocking the ship and having the replacement
paints applied.
If the ship repair contractor supplies the paints, he will be
responsible for all these costs incurred. Hence it is not in the interests
of the ship repair contractor to supply painting compositions.
Drydocking works 11
12 Guide to Ship Repair Estimates (in Man-hours)
Formula to determine the painting area of ship hulls
Input the following data:
LOA in metres xxx
LPP in metres xxx
BM in metres xx
Draft max in metres xx
P = UW constant for type of hull
(0.7 for fine hulls, 0.9 for tankers) 0.x
Height of boot-top in metres xx
Height of topsides in metres xx
N = constant for topsides for type of hull (0.84–0.92) 0.xx
Height of bulwarks in metres xx
Underwater area including boot-top
Boot-top area
Topsides area
Bulwarks area
Underwater area including boot-top
Area = {(2 × draft) + BM)} × LPP × P (Constant for vessel shape)
Boot-top area
Area = {(0.5 × BM) + LPP} × 2 × height of boot-top
Topsides area
Area = {LOA + ( 0.5 × BM)} × 2 × height of topsides
Bulwarks area (Note: external area only)
Area = {LOA + ( 0.5 × BM)} × 2 × height of bulwarks
Using the above formulae, it is a simple matter to formulate a spreadsheet
to determine the external painting areas of the vessel. Input the
data into the table and use the formulae to determine the external
painting areas of the vessel.
Rudder works
Table 2.3 Removal of rudder for survey
(a) Repacking stock gland with owner’s supplied packing. Measuring
clearances, in situ.
(b) Disconnecting rudder from palm and landing in dock bottom for
survey and full calibrations. Refitting as before on completion.
Man-hours
DWT (a) (b)
>3,000 15 165
5,000 18 250
10,000 20 280
15,000 25 300
20,000 28 350
30,000 30 400
50,000 35 500
80,000 45 600
100,000 60 800
150,000 75 900
200,000 90 1,000
250,000 110 1,200
350,000 120 1,500
Drydocking works 13
14 Guide to Ship Repair Estimates (in Man-hours)
Propeller works
Table 2.4 Propeller works (fixed pitch) – 1
(a) Disconnecting and removing propeller cone, removing propeller
nut, setting up ship’s withdrawing gear, rigging and withdrawing
propeller and landing in dock bottom. On completion, rigging and
refitting propeller as before and tightening to instructions of
owner’s representative. Excluding all removals for access, any
other work on propeller and assuming no rudder works.
(b) Transporting propeller to workshops for further works and returning
to dock bottom on completion.
Man-hours
Shaft dia. (mm) (a) (b)
Up to 100 20 15
100–200 30 18
200–300 45 25
300–400 60 30
400–800 90 60
800–900 150 100
Table 2.5 Propeller works (fixed pitch) – 2
(a) Receiving bronze propeller in workshop, setting up on calibration
stand, cleaning for examination, measuring and recording full set
of pitch readings. Polishing propeller, setting up on static balancing
machine, checking and correcting minor imbalances.
(b) Heating, fairing, building up small amounts of fractures and
missing sections, grinding and polishing.
Drydocking works 15
Man-hours
Dia. (mm) Manganese Bronze Aluminium Bronze
Up to 400 15 21
400–800 32 42
800–1200 52 68
1200–1800 75 85
1800–2000 90 105
2000–2500 100 125
2500–3000 130 150
3000–4000 150 180
4000–5000 180 210
Note: Covers repairs outside 0.4 blade radius only; classed as minor repair.
Figure 4 The rudder and propeller of a small vessel in dry dock
Table 2.6 Propeller polishing in situ (fixed pitch)
Polishing in situ using high-speed disc grinder, coating with oil; ship
in dry dock.
Dia. (mm) Man-hours
Up to 400 6
400–800 11
800–1200 17
1200–1800 25
1800–2000 28
2000–2500 35
2500–3000 50
3000–4000 80
4000–5000 120
16 Guide to Ship Repair Estimates (in Man-hours)
Figure 5 A propeller undergoing tests
Tailshaft works
Table 2.7 Tailshaft/sterntube clearances
Removing rope-guard, measuring and recording wear-down of tailshaft
and refitting rope-guard, including erection of staging for
access, by:
(a) Feeler gauge.
(b) Poker gauge coupled with jacking up shaft.
(c) Repacking internal sterngland using owner’s supplied soft
greasy packing.
Man-hours
Tailshaft dia. (mm) (a) (b) (c)
Up to 150 10 15 7
150–250 15 22 11
250–300 21 30 14
300–400 30 40 30
400–800 35 45 35
800–1200 50 55 –
1200–1800 – 57 –
1800–2000 – 60 –
Drydocking works 17
Table 2.8 Removal of tailshaft for survey
Disconnecting and removing fixed-pitch propeller and landing in dock
bottom
(a) Disconnecting and removing tapered, keyed, inboard tailshaft
coupling, drawing tailshaft outboard and landing in dock bottom
for survey, cleaning, calibrating and refitting all on completion.
(b) Disconnecting inboard intermediate shaft fixed, flanged couplings,
releasing one in number journal bearing holding down
bolts, rigging intermediate shaft, lifting clear and placing in temporary
storage on ship’s side. Assuming storage space available.
Withdrawing tailshaft inboard, hanging in accessible position,
cleaning, calibrating and refitting on completion. Relocating intermediate
shaft and journal bearing in original position, fitting all
holding-down bolts and recoupling flanges all as before.
Includes erection of staging for access.
Includes repacking inboard gland using owner’s supplied, conventional
soft greasy packing.
Excludes any repairs.
Excludes any work on patent gland seals.
Man-hours
(a) Withdrawing (b) Withdrawing
Tailshaft Dia. (mm) tailshaft outboard tailshaft inboard
Up to 150 90 140
150–250 120 180
250–300 200 250
300–400 300 400
400–800 500 600
800–1200 – 1000
1200–1800 – 1200
18 Guide to Ship Repair Estimates (in Man-hours)
Crack detection
● Magnaflux testing of tailshaft taper and key way.
● Allowance made of 8 man-hours for the testing works, which is
performed after all removals for access.
Table 2.9 Gland and Simplex-type seal
(a) Removing gland follower, removing existing packing from internal
stern gland, cleaning out stuffing box and repacking gland
using owner’s supplied conventional soft greasy packing.
(b) Disconnecting and removing forward and aft patent mechanical
seals (Simplex-type). Removing ashore to workshop, fully
opening up, cleaning for examination and calibration.
Reassembling with new rubber seals, owner’s supply.
(b) Excluding all machining works.
(b) Assuming previous withdrawing of tailshaft.
Man-hours
Tailshaft Dia. (mm) (a) (b)
Up to 150 8 –
150–250 12 –
250–300 15 35
300–400 23 50
400–800 30 110
800–1200 35 150
1200–1800 – 200
1800–2000 – 230
Drydocking works 19
20 Guide to Ship Repair Estimates (in Man-hours)
Anodes
Table 2.10 Anodes on hull and in sea chests
Cutting off existing corroded anode, renewing owner’s supplied zinc
anode by welding integral steel strip to ship’s hull. Excluding all
access works.
Weight (kg) Man-hours
3 1
5 1
10 1.5
20 2
To determine the amount of anodes required for a vessel, the owner
should contact a supplier who will calculate the exact requirement.
The following shows the method of determining weights of zinc
anodes. (See also the section on hull painting for determining the
underwater area of ships’ hulls.)
Formula to determine the weight of sacrificial zinc anodes required
on a ship’s underwater area
Underwater area of ship in square metres xxx,xxx
Number of years between anode change 3
Capacity of material in amp hours/kg 781
Current density of material in mA/m2 (ave. 10–30 ) 20
K 8760
Formula for total weight of sacrificial zinc anodes (kg) =
Current amps × design life (years) × K (8760)
Capacity of material (amp hours/kg)
Where: Current amps =
Underwater area (m2) × Current Density
1000
Current density of material in mA/m2 =
Information from manufacturer (between 10 and 30, say 20)
Design Life =
Number of years between dry dockings (e.g. 3)
K =
Number of hours in 1 year = 8760
Capacity of material (amp hours / kg) =
Information from manufacturer (781 is common)
Using the above formula, it is a simple matter to create a spreadsheet
to determine the weight of zinc anodes.
Input the data into the table and use the formula to determine
the weight of zinc anodes for the period required.
Drydocking works 21
Sea chests
Table 2.11 Sea chests and strainers
Opening up of sea chests by removing ship side strainers, cleaning
and painting with owner’s paints, as per hull treatment specification.
Assuming single grid per chest.
Surface Area m2 Man-hours
Below 0.3 12
0.3–1 20
Above 1 30
Additional charge per extra grid 5
Docking plugs
Allowance made of 1 man-hour for removing and later refitting of
each tank drain plug using ship’s spanner, assuming no locking
devices fitted and excluding all removals for access and repairs to
threads.
22 Guide to Ship Repair Estimates (in Man-hours)
Drydocking works 23
Valves
Table 2.12 Sea valves
Opening up hand-operated, globe and gate valve for in situ overhaul
by disconnecting and removing cover, spindle and gland, cleaning all
exposed parts, hand grinding of globe valve, light hand scraping of
gate valve, testing bedding, painting internal exposed areas and
reassembling with new cover joint and repacking gland with conventional
soft packing.
(a) Butterfly valve: remove, clean, check, testing bedding of seals,
paint internal exposed areas and refit; excluding operating gear.
(b) Checking and cleaning large butterfly valves through the sea
chest.
Valve bore Globe Gate (a) Butterfly (b) Butterfly
(mm) valve valve valve valve
>50 4 4.5 6 –
100 6 7 8.5 –
150 8 9 11.5 –
200 10 11 14 –
250 13 14 18 –
300 16 17 22 –
350 20 21 26 13
400 23 24 29 14
450 26 28 33 14.5
500 30 31 37 15
550 34 35 42 16
600 37 39 46 16.5
650 41 43 51 17
700 44 47 56 18
750 47 49 60 19
800 50 53 66 20
900 57 60 81 22
1000 65 68 100 24
1100 73 77 106 25
1200 84 88 113 27
1300 95 100 120 30
24 Guide to Ship Repair Estimates (in Man-hours)
Notes:
Valves in pump rooms, additional 15%.
Valve in cofferdams and inside tanks, additional 20%.
Removals for access not included.
Staging for access not included.
Removing valve ashore to workshop for the above type of overhaul requires
special consideration, dependent upon size. Valves below 20 kg in weight
can be assessed as double the in situ rate. Above this requires rigging and
cranage input, which should be assessed separately.
Table 2.13 Ship side storm valves
Opening up ship side storm valve for in situ overhaul, by disconnecting
and removing cover, spindle and gland, cleaning all exposed
parts, testing bedding, painting internal exposed areas and reassembling
with new cover joint and repacking external gland with conventional
soft packing.
Dia. (mm) Man-hours per valve
50 9
75 10
100 12
125 14
150 16
200 17
Note: Disconnecting and removing ashore for above overhaul and later refitment;
double the above rate.
Fenders
Table 2.14 Hollow fenders in half schedule 80 steel pipe
Fendering formed by cutting steel pipe into two halves.
Cropping existing external damaged fendering, hand grinding
remaining edges and preparing remaining flat hull plating for
welding.
Supplying and fitting new fendering in half-round standard schedule
80 steel pipe and full fillet welding fender in place.
Including erection of staging for access and later dismantling.
Exclusions:
All hull preparation and painting of the steelworks in way of the
repairs.
Man-hours per metre
Pipe dia. (mm) Straight run of fender Curved fender at corners
200 20 30
250 22 32
300 24 34
350 26 36
Note: The above figures are for split steel pipe only. For other shapes, then
steel fabrication tariffs will be applicable, based upon steel weights.
Drydocking works 25
Anchors and cables
Table 2.15 Anchor cables (per side)
Ranging out for examination and later restowing
Cleaning by high-pressure jetwash or grit sweeping
Calibration of every 20th link and recording
Marking shots with white paint
Painting cables with owner’s supplied bitumastic paint
Opening ‘Kenter’-type shackle and later closing
Disconnect first length of cable and transferring to end
Changing cable end for end.
Small vessels
Cable dia. (mm) Man-hours (per side)
< 25 70
25–50 90
Large cargo vessels and oil tankers
DWT Man-hours (per side)
< 20,000 100
20,000–50,000 130
50,000–100,000 140
100,000–200,000 200
200,000–300,000 250
over 300,000 270
26 Guide to Ship Repair Estimates (in Man-hours)
Chain lockers
Table 2.16 Chain lockers (per side)
Opening up, removing dry dirt and debris, handscaling, cleaning and
painting one coat bitumastic. Closing up on completion.
Removing internal floor plates, or grating, cleaning, painting and
refitting.
Small vessels
Cable dia. (mm) Man-hours (per side)
< 25 75
25–50 90
Large cargo vessels and oil tankers
DWT Man-hours (per side)
< 20,000 100
20,000–50,000 130
50,000–100,000 140
100,000–200,000 200
200,000–300,000 250
over 300,000 270
Note: Removal of sludge will be charged extra per m3.
Drydocking works 27
Staging
This item is usually charged within a particular job. When included
within the charge of a job, that job price is increased accordingly.
However, to assist estimating, it can be based on cubic metres of air
space covered. A minimum charge of approximately 8 m3 will be
made.
The figures stated in Table 2.17 cover for erection and later dismantling
and removal of external staging. For internal staging, inside
tanks, engine rooms, etc. a third column is shown.
Table 2.17 Erection of tubular steel scaffolding, complete with all
around guard rails, staging planks and access ladders
Man-hours/m3
m3 External Internal
Up to 10 3 5
10–100 2.5 4
100–> 2 3
28 Guide to Ship Repair Estimates (in Man-hours)
3 Steel works
Steel repairs
Applicable to Grade A shipbuilding steels
● Marking off the external area of hull plating on vertical side up to
a height of 2 metres, cropping by hand burning and removal of all
cropped plating.
● Dressing and preparation of plate edges of remaining external
plating.
● Dressing and preparation of remaining internal structure.
● Supply and preparation of new flat steel plating, blasting to Sa2.5
and applying one coat of owner’s supplied, holding primer.
● Transportation of new plate to vessel, fitting up, wedging in position,
minor fairing and dressing of plate edges in the immediate
vicinity, applying first runs of welding on one side, back gouging
from other side and finally filling and capping to give fully finished
weld.
Included in the tariff are:
● Only the work to the steelwork mentioned.
● Cleaning and chipping paint in the immediate vicinity of the
repair area to facilitate hot cutting work.
● Cranage and transportation of the new and removed steelwork.
Exclusions:
● Staging for access. For staging charges see relevant section.
● All removals for access and later refitments.
● Tank cleaning and gas freeing.
● Cleaning in way of repairs other than the immediate vicinity as
noted above.
Steel works 29
● All final tests to repairs.
● Fairing of adjacent plates except as minor in the immediate vicinity
as noted above.
Man-hours are per tonne of finished dimensions. The rates shown are
for large quantities of steel renewals. The limit will be given by the
shipyard and is dependent upon the size of the repair yard and the
vessel. Assume the limit to be approximately 5 metric tonnes.
Shipowner’s superintendents should be aware of the methods
used by the shipyards of calculating steel weights, and this is illustrated
below.
Flat steel plate
● For flat steel plates, measure the length in metres, the width in
metres and the plate thickness in millimetres.
● Take the specific gravity of the material. For steel, the SG is 7.84,
but it is common practice for estimators to use 8.
● To calculate the weight of the plate in kg:
Multiply L × W × Th × SG
For example:
Plate no. L (m) W (m) Th (mm) SG Wt (kg)
1234 1 1 10 8 80
FLAT PLATE
L × W × Th × SG = Weight in kg
ANGLE
L × (W1 + W2) × Th × SG = Weight in kg
30 Guide to Ship Repair Estimates (in Man-hours)
Steel angle
For flat steel angles, measure the length in metres, the widths of each
leg in metres, and the common thickness in millimetres. Take the
specific gravity of the material. For steel, the SG is 7.84, but it is
common practice for estimators to use 8. To calculate the weight of
the steel angle in kg:
Multiply L × (W1 + W2) × Th × SG
For example:
Angle no. L (m) W1 (m) W2 (m) Th (mm) SG Wt (kg)
1111 1 0.150 0.175 10 8 26
For other steel sections, break each down into separate flat sections,
calculate individually and finally add together to obtain the total
weight of the section.
Steel works 31
Figure 6 Repair of damage to shell plating
Table 3.1 Steel works renewals
Plate thickness (mm) Man-hours per tonne
Up to 6 250
8 245
10 240
12.5 230
16 220
18 210
20 200
Correction for curvature Factor increase
Single 1.2
Double 1.3
Correction for location – external Factor increase
Flat vertical side above 2 metres in height
and requiring staging for access 1.1
Bottom shell, accessible areas (i.e. no
removals of keel blocks) 1.12
Keel plate 1.4
Garboard plate 1.25
Bilge strake 1.25
Deck plating 1.15
Correction for location – internal Factor increase
Bulkhead 1.2
Longitudinal/transverse above DB areas 1.25
Longitudinal/transverse below DB areas 1.35
32 Guide to Ship Repair Estimates (in Man-hours)
Other adjustment factors Man-hour adjustment
For fairing works:
Remove, fair and refit 80% of renewal price
Fair in place (if practicable) 50% of renewal price
Note: For high-tensile grade AH shipbuilding steels, increase rates by 10%.
Notes for steel works renewals
● The steel weight is calculated from the maximum dimensions of
each single plate and applying a specific gravity of 8.
● Staging for access and cranage is normally included within the
price differences for repair locations. This should be checked with
the contractor.
● A minimum quantity of steel renewals per area is usually stated in
a ship repairer’s tariff or conditions and is dependent upon the size
of the shipyard and of the vessel. Below this minimum weight per
area, the repairer will either charge anything up to double the standard
tariff or will charge labour time and materials.
● If a plate is being joined to an adjacent plate of different thickness,
then an additional labour charge will be made for taper grinding
of the thicker plate to suit.
Steel works 33
4 Pipe works
Table 4.1 Pipe work renewals in schedule 40 and schedule 80
seamless steel
Removal of existing pipe and disposal ashore. Fabrication of new
pipe in workshop to pattern of existing complete with new flanges,
delivery on board of new pipe and installation in place with the supply
of new soft jointing and standard material fastenings. Refitment of
original clamps with new standard material fastenings.
Inclusions:
● Pipes in straight lengths, no branches, and with 2 flanges. Up to
50 mm nominal bore pipes can be screwed. Above 50 mm
nominal bore pipes can be supplied with slip on welded flanges.
● Pipes readily accessible on deck or in engine rooms above floor
plate level.
Exclusions:
● Access works.
● Removals for access. This also includes other pipes in the way.
● Any cleaning works.
● Heating coils. These are subject to special consideration.
● Any necessary staging or access works.
Man-hours per metre
Pipe dia Schedule 40 Schedule 80
(inches) steel straight pipe steel straight pipe
> 0.5 2 2.3
1 2.5 2.6
1.5 3.2 3.9
2 4.2 5
Pipe works 35
Man-hours per metre
Pipe dia Schedule 40 Schedule 80
(inches) steel straight pipe steel straight pipe
2.5 5.2 6.5
3 6.3 8
4 8.4 10
5 10.5 13
6 12.5 16
8 16.5 21
10 21 26
12 25 31
14 29 37
16 34 42
18 38 47
20 42 53
22 46 58
24 50 64
Notes:
A minimum charge to be applied for length of pipe of 3 metres.
Per bend add 30% of the value of the straight pipe.
Per branch add 80% of the value of the straight pipe.
Removal and refitment only of the pipe, charge is 40% the value of the pipe.
For pipes in other locations, the following additional charges to be
made :
Inside double bottom tanks and duct keels 30%
Inside cargo or ballast tanks 30%
Inside pump rooms 30%
In engine rooms below floor plate level 20%
Galvanizing
Hot dip galvanizing after manufacture.
15% of finished steel pipes.
Ready galvanized pipes
20% of finished steel pipes.
36 Guide to Ship Repair Estimates (in Man-hours)
Copper pipes
Pipe work renewals in copper. The rate for copper pipe renewals is
estimated as 300% that of schedule 40 steel pipes.
Pipe works 37
Figure 7 Main engine cooling-water pipes
Table 4.2 Pipe clamps
Supply and fitting of new pipe clamps together with the supply of new
standard material fastenings. Including welding of clamp to ship’s
structure.
Pipe dia. (inches) Man-hours per renewal of pipe clamp
> 3 2
4 2.5
5 3
6 3.5
8 4
10 5
12 6
14 8
16 9
18 11
20 12
22 13
24 14
38 Guide to Ship Repair Estimates (in Man-hours)
Table 4.3 Spool pieces
Removal of existing steel penetration pieces from bulkheads or
decks, fabrication and installation of new straight, seamless steel,
penetration pieces with two flanges and one flat bulkhead compensation
flange welded in place. Including supply and installation of soft
joint and standard material fastenings.
Man-hours per spool piece
Pipe dia. Schedule 40 Schedule 80
(inches) steel straight pipe steel straight pipe
> 0.5 2 2.5
1 3.5 4.3
1.5 5.5 6.8
2 9 11.2
2.5 10 12.5
3 12.5 15.5
4 15 18.7
5 17 21
6 19 24
8 29 36
10 35 44
12 42 52
14 51 64
16 62 77
18 73 91
20 85 105
24 95 118
Note: The same conditions apply to these spool pieces as for pipe renewals.
Pipe works 39
5 Mechanical works
In the following mechanical works it is assumed that all are in situ
overhauls and that the items considered are all accessible for the
work to be performed.
If any item is to be removed ashore to the workshops then an
assessment of the work involved must be made and the rates given
amended accordingly. This is considering removals to permit transportation
of the item from the ship and their later refitment, on completion
of the reinstallation.
Mechanical works 41
Overhauling diesel engines (single-acting,
slow-running, two-stroke, cross-head)
In the overhauling of large main propulsion engines, it is assumed
that the ship will provide all the specialized equipment necessary.
This refers to heavy-duty equipment which is normally supplied by
the engine manufacturer and also any special hydraulic tensioning
equipment for fastenings. In main engines, it is assumed that there
are lifting devices such as overhead beams, runner blocks and/or
overhead cranes.
42 Guide to Ship Repair Estimates (in Man-hours)
Figure 8 A main propulsion diesel engine
Table 5.1 Top overhaul
Disconnect and remove cylinder head, withdraw piston, remove
piston rings, clean, calibrate and reassemble as before using all
owner’s supplied spares.
Cylinder bore (mm) Man-hours per cylinder
500 67
550 70
600 75
650 80
700 87
750 95
800 105
850 115
900 125
950 137
1000 150
Cylinder cover
Disconnect and remove cylinder head, clean all exposed parts,
including piston crown and reassemble as before using all owner’s
supplied spares.
Assume as 60% the rate of top overhaul rate.
Mechanical works 43
Table 5.2 Cylinder liners – 1
Withdrawing of cylinder liner, cleaning exposed areas as far as
accessible, installing of new, owner’s supplied liner and rubber seals.
Cylinder bore (mm) Man-hours per cylinder
500 60
550 62
600 67
650 72
700 77
750 82
800 90
850 97
900 107
950 120
1000 135
Note: Assuming that cylinder head, piston and piston rod are already
removed as part of the top or complete overhaul.
44 Guide to Ship Repair Estimates (in Man-hours)
Table 5.3 Bearing survey – 1
Opening up for inspection, exposing both halves, cleaning, calibrating
and presenting for survey. On completion, reassembling as
before.
Man-hours/bearing
Cylinder bore (mm) Cross-head Crank pin Main
500 47 32 45
550 50 35 48
600 52 37 50
650 55 40 52
700 57 42 55
750 58 45 56
800 60 47 59
850 62 50 63
900 65 52 67
950 68 55 72
1000 72 57 76
1050 75 60 80
Note: For exposing top half of bearing shell only, charge 60% of above rates.
Table 5.4 Crankshaft deflections – 1
(a) Opening up crankcase door for access works and refitting on
completion.
(b) Setting up deflection indicator gauge, turning engine, using
ship’s powered turning gear and recording observed readings.
Removing equipment and closing up crankcase door on completion.
Mechanical works 45
Cylinder bore (mm) (a) Deflections (b) Crankcase doors
Man-hours per unit Man-hours per door
> 750 4 4
750–850 4.5 4.5
850–950 4.5 5
950–1050 5 5.5
46 Guide to Ship Repair Estimates (in Man-hours)
Overhauling diesel engines (single-acting,
slow-running, in-line, four-stroke, trunk)
In the overhauling of large main propulsion engines it is assumed
that the ship will provide all the specialized equipment necessary.
This refers to heavy-duty equipment which is normally supplied by
the engine manufacturer and also any special hydraulic tensioning
equipment for fastenings. In main engines, it is assumed that there
are lifting devices such as overhead beams, runner blocks and/or
overhead cranes.
Mechanical works 47
Figure 9 A ship’s medium-speed main engine
Table 5.5 Four-stroke trunk-type main engines
(a) Cylinder head: Disconnecting and removing cylinder head, cleaning
all exposed parts, including piston crown and reassembling as
before using all owner’s supplied spares. Disconnecting and removing
2 in number air inlet valves and 2 in number exhaust valves,
including exhaust valve cage with removable seats. Cleaning and
decarbonizing valves, cages and head as far as accessible, lightly
hand grinding valves for examination only of seating areas.
(a) Clarifications:
(a) Work on the seats may be protracted so is excluded. This could
include changing seat inserts, machining and grinding/lapping
seats. It will require establishing and should be subject to work
assessment.
(b) Top overhaul: Disconnect and remove one pair of crankcase doors,
disconnect bottom end bearing fastenings. Disconnect and remove
cylinder head, withdraw piston, remove piston rings, clean, calibrate
and reassemble as before using all owner’s supplied spares.
(c) Piston gudgeon pin: Drawing out gudgeon pin from removed
piston, clean all exposed parts, calibrate and record and reinstall
pin as before. Any spares to be owner’s supply.
Cylinder bore (a) Man-hours (b) Man-hours c) Man-hours
(mm) per cylinder head per cylinder per piston pin
100 16 16 4
150 20 20 4
200 22 24 6
250 24 32 8
300 32 36 10
350 36 40 12
400 40 48 14
450 48 56 16
500 56 64 18
550 64 72 20
600 72 80 24
Note: For Vee bank engines add 20% per unit.
48 Guide to Ship Repair Estimates (in Man-hours)
Table 5.6 Cylinder liners – 2
Withdrawing of cylinder liner, cleaning and painting exposed areas
as far as accessible, installing of new, owner’s supplied liner, or existing
liner, complete with owner’s supplied rubber seals and top joint.
Attending hydrostatic test carried out by ship’s staff.
Cylinder bore (mm) Man-hours per cylinder
100 16
150 20
200 24
250 28
300 32
350 40
400 44
450 48
500 52
550 56
600 60
Mechanical works 49
Table 5.7 Bearing survey – 2
Opening up for inspection, exposing both halves, cleaning, calibrating
and presenting for survey. On completion, reassembling as before.
Man-hours per bearing
Cylinder bore (mm) Crank pin Main
100 6 4
150 8 6
200 10 8
250 14 10
300 16 12
350 18 14
400 20 16
450 24 18
500 28 20
550 32 24
600 36 32
Note: For exposing top half of bearing shell only, charge 60% of above rates.
50 Guide to Ship Repair Estimates (in Man-hours)
Table 5.8 Crankshaft deflections – 2
(a) Opening up crankcase door for access works and refitting on
completion.
(b) Setting up deflection indicator gauge, turning engine, using
ship’s powered turning gear and recording observed readings.
Removing equipment and closing up crankcase door on completion.
Cylinder bore (a) Crankcase doors (b) deflections
(mm) Man-hours per door Man-hours per unit
> 100 4 4
100–200 4 6
200–300 4 8
300–400 6 12
400–500 8 16
500–600 8 20
Mechanical works 51
Valves
Table 5.9 Overhauling valves
Opening up hand-operated, globe and gate valve for in situ overhaul,
by disconnecting and removing cover, spindle and gland, cleaning all
exposed parts, hand grinding of globe valve, light hand scraping of
gate valve, testing bedding, painting internal exposed areas and
reassembling with new cover joint and repacking gland with conventional
soft packing.
For low-pressure valves, below 10 kg/cm2, the tariff is the same
as for sea valves. This also applies to the increases for location.
The following increases can be applied according to the
pressure:
Pressure (kg/cm2) Increase over sea valve tariff (%)
10 100
16 120
20 140
40 160
60 180
80 200
Notes:
Insulation renewal excluded.
Pressure testing in situ using ship’s pump; additional 5 hours per valve.
Pressure testing in situ using contractor’s pump; additional 7 hours per valve.
Removal and overhaul ashore in workshop; double the in situ rate.
Metallic or special packings, owner’s supply; additional 2 hours per valve.
Rates apply to hand-operated valves only.
52 Guide to Ship Repair Estimates (in Man-hours)
Mechanical works 53
Figure 10 A ballast system valve chest
54 Guide to Ship Repair Estimates (in Man-hours)
Figure 11 A standard screw-lift globe valve
Condensers
Table 5.10 Main condenser
Opening up inspection doors, cleaning sea water end boxes and
tubes by air or water lance, test and reclosing.
SHP Man-hours
12,000 120
15,000 140
20,000 160
22,000 180
24,000 200
30,000 220
Note: Excluding stagings for access.
Mechanical works 55
Heat exchangers
Table 5.11 Overhauling heat exchanger
(a) Disconnecting and removing end covers, cleaning water side
end plates and water boxes and tubes by air or water lance, test
and reclosing.
(b) Hydraulic testing: Disconnecting and removing secondary side
pipeworks. Providing necessary blanks and installing. Filling with
fresh water and applying necessary hydraulic pressure test.
Draining on completion, removing blanks and installing pipes as
before.
Man-hours
Cooling water surface area, m2 (a) (b)
>3 16 8
5 20 12
10 24 12
15 32 12
20 36 16
30 40 16
50 44 16
100 56 16
150 64 20
200 80 20
250 88 20
300 96 24
350 108 24
400 120 32
Notes:
Applicable for standard tube type heat exchanger. For plate type, cleaning rates
to be increased by 120%.
Including renewal of owner’s supplied internal sacrificial anode on primary side.
Including painting with owner’s supplied painting composition on primary side.
Excluding any repairs.
Excluding draining secondary side and associated cleaning works.
For ultrasonic cleaning, special considerations to apply.
56 Guide to Ship Repair Estimates (in Man-hours)
Turbines
Table 5.12 Main steam turbines
Opening up for inspection, disconnecting flexible coupling and lifting
up rotor, examining bearings, coupling and rotor, checking clearances,
cleaning jointing surfaces and reclosing.
Man-hours
SHP HP Turbine
12,000 180 210
15,000 220 250
20,000 250 280
22,000 260 300
24,000 270 310
26,000 280 320
32,000 350 400
36,000 430 480
Note: Removal of any control gear is not included. If applicable, increase
rates by 30%.
Table 5.13 Flexible coupling
Disconnecting guard, opening up coupling, cleaning, presenting for
survey and examination, measuring and recording clearances,
closing up. Excluding any repairs, renewals or realignment works.
SHP Man-hours each
12,000 30
15,000 32
20,000 34
22,000 35
24,000 36
26,000 37
28,000 38
Mechanical works 57
SHP Man-hours each
30,000 40
32,000 42
34,000 44
36,000 46
Note: Removals for access are excluded.
Table 5.14 Auxiliary steam turbines
Opening up for in situ inspection, disconnecting flexible coupling and
lifting up turbine rotor, examine bearings, coupling and rotor, check
clearances, clean jointing surfaces and reclose.
Turbo alternator turbine
kw Man-hours each
400 170
700 180
1000 190
1500 200
2000 230
2500 270
Cargo pump turbine
Tonnes/hour (of pump) Man-hours each
>1000 100
>1500 110
>2000 125
>2500 145
>3000 150
>4000 165
>5000 185
58 Guide to Ship Repair Estimates (in Man-hours)
Feed pump turbine
SHP Man-hours each
12,000 42
15,000 48
20,000 56
24,000 60
30,000 64
36,000 68
Notes:
Assume pump and turbine to be horizontal.
For vertical pump, increase by 10%.
Excluding dynamic balance checking.
Table 5.15 Water-tube boiler feed pumps (multi-stage type)
Disconnect and remove upper half of pump casing, disassemble
internals and draw shaft. Clean, inspect and calibrate all parts.
Rebuild rotor, set clearances and refit upper half of casing. All spares
to be owner’s supply.
SHP Man-hours each
12,000 48
15,000 52
20,000 56
24,000 60
30,000 64
36,000 68
Notes:
The above figures apply to overhaul of pump only. If carried out in conjunction
with overhaul of turbine, then reduce figures by 10%.
All access works and insulation works included.
Mechanical works 59
Table 5.16 Oil tanker cargo pumps
Disconnecting and removing top half of casing, releasing shaft flexible
coupling from drive, slinging and removing impeller, shaft and
wearing rings.
Withdrawing impeller, shaft sleeve and bearings from shaft.
Cleaning all exposed parts, calibrating and reporting.
Reassembling as before using owner’s supplied parts, jointing
materials and fastenings.
Tonnes/hour Man-hours each
>1000 90
>1500 100
>2000 110
>2500 125
>3000 140
>4000 150
>5000 160
Notes:
Horizontal centrifugal single-stage type pumps.
For vertical pumps, increase figures by 15%.
Compressors
Table 5.17 Air compressor (two-stage type)
Disconnecting and removing cylinder heads, releasing bottom end
bearings, withdrawing pistons.
Opening up main bearings, including removing crankshaft on compressors
with removable end plate.
Dismantling cylinder head air suction and delivery valves
Cleaning all parts, calibrating and reporting condition.
Reassembling all as before using owner’s supplied spares as
required.
Cleaning of attached air inter-cooler, assuming accessible.
60 Guide to Ship Repair Estimates (in Man-hours)
Capacity (m3/hour) Man-hours per machine
10 50
20 55
50 60
100 70
200 80
300 90
400 100
500 120
600 150
Note: For three-stage compressors, charge rate to be increased by 150%.
Receivers
Table 5.18 Air receivers
Opening up manholes, cleaning internal spaces for inspection, painting
internal areas and closing manholes with owner’s supplied jointing
materials.
Capacity (m3) Man-hours per receiver
<1 16
5 20
10 24
15 28
20 32
30 36
40 40
50 48
60 52
Mechanical works 61
Pumps
Table 5.19 Horizontal centrifugal-type pumps
Disconnecting and removing top half of casing, releasing shaft
coupling from motor drive, slinging and removing impeller, shaft
and wearing rings.
Withdrawing impeller, shaft sleeve and bearings from shaft.
Cleaning all exposed parts, calibrating and reporting.
Reassembling as before using owner’s supplied parts, jointing materials
and fastenings.
Capacity (m3/hour) Man-hours per pump
5 20
10 24
20 32
50 34
100 40
200 48
300 52
500 56
750 60
1000 64
1500 72
Notes:
Assuming single-stage pump.
Assuming driven by an attached electric motor.
For multi-stage turbine-driven pumps, see the rates given for water-tube
boiler feed pumps and assess accordingly.
62 Guide to Ship Repair Estimates (in Man-hours)
Mechanical works 63
Figure 12 A vertical electric-driven centrifugal water pump
Table 5.20 Reciprocating-type pumps, steam driven –
(a) simplex, (b) duplex
Disconnecting and removing steam cylinder top cover, releasing
steam piston, withdrawing, removing piston rings, cleaning, calibrating
and recording.
Disconnecting and removing slide valve cover, removing valves,
cleaning and presenting for survey.
Disconnecting and removing bucket cover, releasing bucket, withdrawing,
removing bucket rings, cleaning, calibrating and recording.
Opening up suction and delivery valve chest, removing valves and
springs, cleaning, grinding and presenting for survey.
Fully reassembling complete pump renewing all jointing and repacking
glands with owner’s supplied conventional soft packing.
Excluding all repairs and renewals.
Man-hours
Capacity of pump (m3/hour) (a)Simplex pump (b) Duplex pump
50 64 112
100 80 140
200 104 182
300 120 210
400 144 252
500 160 280
Table 5.21 Reciprocating-type pumps, electric motor driven –
(a) simplex, (b) duplex
Disconnecting and removing electric motor aside.
Disconnecting and removing bucket cover, releasing bucket, withdrawing,
removing bucket rings, cleaning, calibrating and recording.
Opening up suction and delivery valve chest, removing valves and
springs, cleaning, grinding and presenting for survey.
Fully reassembling complete pump renewing all jointing and repacking
glands with owner’s supplied conventional soft packing.
Reinstalling electric motor and making terminals.
Excluding all repairs and renewals.
64 Guide to Ship Repair Estimates (in Man-hours)
Man-hours
Capacity of Pump (m3/hour) (a) Simplex pump (b) Duplex pump
5 32 56
10 40 72
20 48 80
30 56 96
40 64 112
50 72 120
Table 5.22 Gear-type pumps (helical and tooth)
Disconnecting and removing pump, opening up end covers, withdrawing
gear units, cleaning, calibrating, recording clearances and
presenting for survey.
Fully reassembling pump renewing all jointing and repacking glands
with owner’s supplied packing or seals.
Capacity (m3/hour) Man-hours per pump
1 16
5 24
10 28
20 32
50 48
100 56
200 64
300 72
400 80
500 88
Mechanical works 65
Table 5.23 Steering gear
Variable delivery constant speed electro-hydraulic pumps.
Disconnecting pump and removing for in situ overhaul. Opening up
pump, full dismantling, cleaning calibrating and presenting for survey.
Full reassembling using owner’s supplied spares and reinstalling in
place.
Capacity (HP) Man-hours per pump
3 24
5 32
8 36
10 42
15 48
20 56
25 64
30 72
66 Guide to Ship Repair Estimates (in Man-hours)
Boilers (main and auxiliary)
Table 5.24 Cleaning of water-tube boilers
Opening up gas side of boiler, normal clean all fire side surfaces
using high-pressure fresh water. Removing drain plates from gas
side of boiler to permit drainage of water to bilges and later refitment.
Closing up gas sides as before.
Opening up water side of boiler by removing manhole doors from
water drums, hosing down with fresh water and reclosing.
Man-hours
Vessel SHP Single boiler Two boilers Auxiliary boiler
20,000 453 748 340
22,000 464 766 350
24,000 476 818 360
26,000 504 857 365
Notes:
Allowance made for 10 access doors, 10 hand-hole doors and 2 manholes
per boiler.
Special cleaning of super-heater tubes to be charged additional.
Extra dirty boilers to be charged additional.
Staging not included.
For hydraulic testing of boiler using fresh water; 10% additional charge.
Excluding economizer and superheater.
Mechanical works 67
6 Electrical works
Table 6.1 Insulation resistance test on all main and auxiliary, lighting
and power circuits and report
Vessel DWT Man-hours
<5,000 24
>5,000 40
10,000 48
20,000 56
50,000 64
75,000 64
100,000 72
Electrical works 69
Figure 13 A main electrical switchboard in a machinery control room
Table 6.2 Switchboard
Cleaning behind switchboard, examining all connections and retightening
as necessary, reporting conditions.
Vessel DWT Man-hours
< 5,000 32
> 5,000 40
10,000 50
20,000 75
30,000 100
70 Guide to Ship Repair Estimates (in Man-hours)
Figure 14 A generator control panel in a main switchboard
Table 6.3 Electric motors
Disconnecting motor from location, transporting motor ashore to
workshop for rewinding, and, on completion, returning on board,
refitting in original position and reconnecting original cables.
Receiving motor in workshop, dismantling, cutting out all stator coils,
removing rotor bearings and cleaning all parts. Forming new stator
coils in copper wire assembling using new insulation and varnish.
Baking dry in oven, dip varnishing and rebaking in oven.
Reassembling all parts, fitting new standard type ball or roller bearings
to rotor and testing in workshop.
Capacity (kW) Man-hours
<3 24
5 30
10 38
15 40
20 40
30 48
40 50
50 60
60 75
75 80
100 90
Notes:
Excluding rebalancing of rotor.
These man-hours are for work on AC motors only and these are assumed to
be single-speed, squirrel-cage induction motors, three-phase, 380/440 volts,
50/60 Hz, 1440/1760 rpm, and with Class B insulation.
Excluding: staging for access to location, removals in way, cleaning in way
and cranage.
Electrical works 71
Table 6.4 Electric motors for winch/windlass/crane
Disconnecting motor from location, transporting motor ashore
to workshop for rewinding, and, on completion, returning on
board, refitting in original position and reconnecting original
cables.
Receiving motor in workshop, dismantling, cutting out all stator
coils, removing rotor bearings and cleaning all parts. Forming
new stator coils, for both stators, in copper wire assembling
using new insulation and varnish. Baking dry in oven, dip
varnishing and rebaking in oven. Reassembling all parts, fitting
new standard type ball or roller bearings to rotor and testing in
workshop.
Figure 15 A standard AC induction electrical motor
72 Guide to Ship Repair Estimates (in Man-hours)
Capacity (kW) Man-hours
20 160
30 200
40 220
50 240
60 300
75 320
100 360
Notes:
These man-hours are for work on AC motors only and these are assumed to
be triple-speed, three-phase, 380/440 volts, 50/60 Hz, double rotor/stator,
squirrel-cage induction motors with integral brake with Class B insulation.
Excluding rebalancing of rotor.
Table 6.5 Electric generators
Disconnecting and removing rotor ashore to workshop, full cleaning,
baking in oven, drying, varnishing, rebaking in oven, testing,
reassembling and reconnecting in place on board.
KVA Man-hours
<50 75
51–100 90
101–200 100
300 140
400 160
500 175
600 190
750 200
1000 220
Electrical works 73
Figure 16 A ship’s main diesel-driven AC alternator
74 Guide to Ship Repair Estimates (in Man-hours)
Table 6.6 Installation of electric cables. Man-hours for installations
per 100 metres of unarmoured, flexible, multi-core, rubber-insulated
cable
Area (mm2) 2 core 3 core 4 core 5 core 6 core 7 core 9 core 12 core
0.5 21 25 30 30 34 37 – –
1 23 27 33 34 38 41 – –
1.5 25 33 49 57 65 82 – –
2.5 43 49 54 66 78 90 106 122
4 48 53 61 72 89 106 129 150
6 54 61 66 79 – 115 – –
10 61 72 77 – – – – –
Including:
● Handling and installing in place numbers of lengths as indicated
of electric cable.
● Stripping back cable and insulation and preparing for connecting.
● Connecting to existing junction boxes in existing cable tray with
new cable ties.
● Man-hours shown are for installation of exposed cables up to
heights of 3 metres on exposed flat surfaces in existing cable
trays.
Exclusions:
● Material costs. These figures show man-hour charges only.
● Any removals of existing, or old cable. These man-hours are for
new installations only.
● Installation of scaffolding and any access work. These to be
covered in separate sections.
Notes:
Man-hours shown are for the installation of a single length of cable.
For the installation of a parallel, second length of electric cable, reduce by
15%.
For the installation of a parallel, third length of electric cable, reduce by 25%.
For the installation of a parallel, fourth length of electric cable, reduce by
Electrical works 75
30%.
For the installation of a parallel, fifth and subsequent length of electric cable,
reduce by 35%.
For additional height, increase tariff as follows:
3–5 metres; increase by 5%
5–8 metres; increase by 10%
8–12 metres; increase by 15%
76 Guide to Ship Repair Estimates (in Man-hours)
Table 6.7 Man-hours for installations per 100 metres of rubberinsulated,
or similar, armoured flexible cable, braided in bronze or
steel, basket weave
Area (mm2) 2 core 3 core 4 core 5 core 6 core
1 28 36 40 45 51
1.5 29 39 51
2.5 46 59 67
4 53 67 74
6 74 86 92
10 82 90 94
16 86 93 99
25 90 95 109
35 95 99 120
50 99 112 141
70 104 132 164
95 109 141 180
120 128 167 205
150 132 176 218
185 154 205 256
240 196 261 326
300 254 352 440
Including:
● Handling and installing in place numbers of lengths as indicated
of electric cable.
● Stripping back cable and insulation and preparing for connecting.
● Connecting to existing junction boxes in existing cable tray with
new cable ties.
● Man-hours shown are for installation of exposed cables up to
heights of 3 metres on exposed flat surfaces in existing cable
trays.
Exclusions:
● Material costs. These figures show man-hour charges only.
● Any removals of existing, or old cable. These man-hours are for
new installations only.
Electrical works 77
● Installation of scaffolding and any access work. These to be
covered in separate sections.
Notes:
Man-hours shown are for the installation of a single length of cable.
For the installation of a parallel, second length of electric cable, reduce by
15%.
For the installation of a parallel, third length of electric cable, reduce by 25%.
For the installation of a parallel, fourth length of electric cable, reduce by
30%.
For the installation of a parallel, fifth and subsequent length of electric cable,
reduce by 35%.
For additional height, increase tariff as follows:
3–5 metres; increase by 5%
5–8 metres; increase by 10%
8–12 metres; increase by 15%
78 Guide to Ship Repair Estimates (in Man-hours)
Figure 17 Grouping of electric cables on a cable tray
Table 6.8 Man-hours for installations per 100 metres of rubberinsulated,
or similar, armoured flexible cable, braided in bronze or
steel, basket weave. Single-core cable (for use with multi-runs of
higher cable sizes)
Area (mm2) 1 wire 2 wires 3 wires 4 wires 5 wires
50 80 88 102 122 157
70 92 102 117 140 182
95 108 119 137 163 213
120 125 137 157 189 246
150 132 145 166 200 260
185 148 163 188 225 293
240 174 191 220 263 342
300 231 254 293 351 456
380 281 310 356 427 556
Including:
● Handling and installing in place numbers of lengths as indicated
of electric cable.
● Stripping back cable and insulation and preparing for connecting.
● Connecting to existing junction boxes in existing cable tray with
new cable ties.
● Man-hours shown are for installation of exposed cables up to
heights of 3 metres on exposed flat surfaces in existing cable
trays.
Exclusions:
● Material costs. These figures show man-hour charges only.
● Any removals of existing, or old cable. These man-hours are for
new installations only.
● Installation of scaffolding and any access work. These to be
covered in separate sections.
Notes:
Man-hours shown are for the installation of single runs of cable without joins.
For additional height, increase tariff as follows:
3–5 metres; increase by 5%
5–8 metres; increase by 10%
8–12 metres; increase by 15%
Electrical works 79
Table 6.9 Man-hours for installations of cable tray per metre
(perforated steel cable tray, including brackets and fastenings)
Size (mm) Man-hours per metre
75 0.95
100 1.05
150 1.25
225 1.50
300 1.75
Bends Each bend to be rated at
three times that of ‘per
metre’
Including:
● Handling and installing in place numbers of lengths as indicated
of electric cable tray.
● Man-hours shown are for installation of exposed cable tray up to
heights of 3 metres on exposed flat surfaces.
Exclusions:
● Material costs. These figures show man-hours charges only.
● Any removals of existing, or old cable tray. These man-hours are
for new installations only.
● Installation of scaffolding and any access work. These to be
covered in separate sections.
Notes:
Man-hours shown are for the installation of a single length of cable tray.
For additional height, increase tariff as follows:
3–5 metres; increase by 5%
5–8 metres; increase by 10%
8–12 metres; increase by 15%
80 Guide to Ship Repair Estimates (in Man-hours)
Electrical works 81
Figure 18 Control panels of a ship’s auxiliary equipment
Table 6.10 Man-hours for installations of electric cable conduit
per metre (galvanized steel conduit, including brackets and
fastenings)
Size (mm) Man-hours per metre
20 0.72
25 0.78
32 1.14
Including:
● Handling and installing in place numbers of lengths as indicated
of electric cable conduit.
● Man-hours shown are for installation of exposed cable conduit up
to heights of 3 metres on exposed flat surfaces.
Exclusions:
● Material costs. These figures show man-hours charges only.
● Any removals of existing, or old cable conduit. These man-hours
are for new installations only.
● Installation of scaffolding and any access work. These to be
covered in separate sections.
Notes:
Man-hours shown are for the installation of a single length of cable conduit.
For additional height, increase tariff as follows:
3–5 metres; increase by 5%
5–8 metres; increase by 10%
8–12 metres; increase by 15%
82 Guide to Ship Repair Estimates (in Man-hours)
7 General works
Table 7.1 General cleaning
(a) Berthing vessel alongside special tank cleaning berth.
(b) Receiving of bilge water or slops into shore facility using ship’s
pumps.
(c) Removing sludge deposits from tanks and disposal ashore.
(a) Man-hours (b) Man-hours (c) Man-hours
(minimum per 20 tonnes per 10 tonnes
charge) (minimum) (minimum)
150 1.5 105
Notes:
(a) This rate may vary depending upon shipyard. An hourly rate will apply
with a minimum charge being levied, as shown in the figure above.
(b) The rate for collection of bilge water or slops will depend upon the
receiving facility and the rate levied for (a). For collection by road tankers,
separate quote should be requested.
General works 83
Table 7.2 Tank cleaning
(a) Removal of tank manhole cover for access and refitting with new
cover joint.
(b) Removing dirt and debris cubic metre.
(c) Hand cleaning of bilge areas or inside tanks per 10 square
metres.
(d) Hand scraping of internal steel areas per 10 square metres.
Man-hours
Type of tank (a) (b) (c) (d)
Fresh water 6 0.70 1.25 1.0
Ballast water 6 6.3 1.60 1.70
Fuel oil (MGO) 6 10.5 4.25 –
Table 7.3 Tank testing
(a) Tank testing by low pressure compressed air, per tonne
capacity.
(b) Tank testing by filling with sea water, per tonne capacity.
Man-hours
Tank capacity (m3) (a) (b)
< 5 0.25 0.32
5–20 0.20 0.25
20–50 0.16 0.20
50–100 0.14 0.16
Special notes on quotations:
● Obtain a copy of the ship repair contractor’s standard tariff rates.
● Request the ship repair contractor to agree that extra work will be
priced in accordance with produced standard tariffs, or other
agreed rates.
● Ensure that conditions of contract are agreed before placing of contract.
If not, then it will be assumed that the shipyard’s standard conditions
apply, which may not always be suitable to the ship owner.
84 Guide to Ship Repair Estimates (in Man-hours)
8 Planning charts
The following is not necessarily required by ship owner’s superintendents,
but may prove useful to give an indication as to a method
of determining the timescale and daily loadings for carrying out the
repairs.
In forward planning and scheduling it is imperative that the
planned timescale for repair periods are adhered to strictly in order
to avoid knock-on effect delays. A ship repair yard therefore must be
aware, well in advance, of the total work load and resources needed
to complete each job. This is where the man-hour totals for each
trade are required and, very importantly, the work rate of each trade.
The graphs shown in this section have been compiled from historical
data by shipyard workload planners and are actual graphs
derived, and used by, a large international ship repair yard to assist
the forward planning of the yard. The yard’s planners must ensure
that sufficient resources are available to carry out the workload,
looking up to 3 months ahead and this is their method of doing so.
Using this process the planners can arrange for the necessary
resources to be available well ahead of the scheduled repair period
and have these available on arrival of the vessel.
Using a prepared ship repair specification, a planner will carry
out an analysis of the work and produce a critical path. This critical
path determines the timescale of the repair period, so any way in
which the timescale of a job within the critical path may be reduced
will reduce the overall timescale. Additional resources will be used
on these jobs to ensure their earlier completion, so then this is the
way in which the total timescale is reduced.
Using the foregoing tables in this book, the estimator can forecast
the total number of man-hours per trade for the specified work.
Knowing the yard’s resources, the next job is to develop the daily
work rate for each trade.
A graph of the work rate for each trade is available with the
Planning charts 85
yard’s planners, and using the graphs, the planner can estimate the
timescale to complete the known works.
In carrying out a planned repair period, the planner will consider
certain aspects of priority.
As an example, consider a vessel entering the dry dock and a
number of trades have planned work in the dry dock area. A very
high work rate is necessary to complete any work that prevents other
trades from carrying out their work. Into this category comes the
hull treatment workers. These are the first workers on the external
areas of the vessel. This trade will hand scrape the hull free from sea
growth and then carry out high-pressure jetwashing of the hull.
Preparations will then be made for this trade to continue with gritblasting
to clean the hull and then apply the first coat of primer paint.
Once this high activity area has been completed, the work rate of the
hull treatment trade may be reduced to make way for other trades to
carry out their external work. The hull treatment trade workload may
now be reduced, and certain of these workers released to other high
activity areas.
During this period, very few other trade workers will be able to
work in the same vicinity, so the planners assign these to other areas.
The trade graph will indicate the high work rate of the hull treatment
workers initially on the hull and then show the tapering off.
All trades are considered in a similar manner and graphs drawn
from historical data until the work rate of each trade can be predicted.
The graphs have been drawn up indicating the trend of work rate
of the individual trades and are used to determine the timescale of the
repair period.
Conflicts always occur in repair period. As noted with the hull
treatment, no other trade can work during this period, so this is a conflict
in this area. There are many conflicts between trades and also
within trades, causing delays in starting jobs, and continuing jobs.
The jobs on the critical path generally are given a higher priority than
other jobs by the overall co-ordinator of the work.
The following example describes the method of using the workload
graphs :
As an example, take the marine fitter graph.
The estimator/planner will have determined the total man-hours for
the complete specified works so will have a grand total.
86 Guide to Ship Repair Estimates (in Man-hours)
Knowing the available resources at the yard, the maximum
number allocated to a ship will be known, e.g. 10 men.
The percentage work is an estimated total, e.g. 1000 man-hours.
Each man may be assigned to work 10 hours per shift.
So the logical time to complete the works will be :
1000 man-hours/10 men x 10 hours per shift = 10 shifts. When this
is determined, a decision will be made on whether this time is excessive
and, if so, additional resources will be assigned. If not then it will
continue as planned.
10 men x 10 hours per shift = 100 man-hours per shift, should be
10% of the work per shift. Carrying out this constant work rate would
produce a straight line graph at 45° where the slope would be
‘y’ = ‘x’.
However, this does not happen and is shown from the marine fitter
graph as follows:
Each work shift comprises 100 man-hours.
The first shift’s work will complete 5% of the work.
The second shift’s work will continue up to 14% of the work, an
increase of 9%.
The third shift’s work will continue up to 31% of the work, an increase
of 17%.
The fourth shift’s work will continue up to 43% of the work, an
increase of 12%.
The fifth shift’s work will continue up to 55% of the work, an increase
of 12%.
The sixth shift’s work will continue up to 67% of the work, an increase
of 12%.
The seventh shift’s work will continue up to 81% of the work, an
increase of 14%.
The eighth shift’s work will continue up to 88% of the work, an
increase of 7%.
The ninth shift’s work will continue up to 95% of the work, an
increase of 7%.
The tenth shift’s work will continue up to 100% of the work, an
increase of 5%.
This indicates the varying degrees of output for the same man-hour
input. This is caused by the type of conflicts shown in the hull treatment
workers, where other trades must allow them sole access to
certain areas.
Planning charts 87
The trade supervisors, together with the planners, may increase or
decrease the quantity of workers in certain areas to allow smooth
running of the work.
This is one use of the graphs. Another is where a vessel must be
completed within a certain timescale and the graphs are used to indicate
the numbers of workers per trade that must be used in order to
meet the target date. Knowing this, if the yard do not possess the full
resources themselves, then the planners can ascertain the numbers
of sub-contracted labour that are required to complete the total work
schedule.
In this instance the timescale will be a known entity, so then it will be
established what are the exact number of man-hours per shift per
trade to complete the work in accordance with the work rate of the
trade graph. A histogram would then be drawn indicating the
number of men per trade per shift, and these resources would be
allocated well in advance of the arrival date of the vessel.
To illustrate this, again take the case of the marine fitters having a
workload of 1000 man-hours and an exact time of 10 shifts is allocated
to complete the job :
The first shift’s work will complete 5% of the work = 50 man-hours.
The second shift’s work will complete 9% = 90 man-hours.
The third shift’s work will complete 17% = 170 man-hours.
The fourth shift’s work will complete 12% = 120 man-hours.
The fifth shift’s work will complete 12% = 120 man-hours.
The sixth shift’s work will complete 12% = 120 man-hours.
The seventh shift’s work will complete 14% = 140 man-hours.
The eighth shift’s work will complete 7% = 70 man-hours.
The ninth shift’s work will complete 7% = 70 man-hours.
The tenth shift’s work will complete 5% = 50 man-hours.
Total man-hours = 1000.
Total shifts = 10
The manpower input is variable in accordance with the graph work
rate loading.
The workers can therefore be assigned against the shift man-hour
totals necessary to complete each shift’s total workload.
88 Guide to Ship Repair Estimates (in Man-hours)
The following histogram indicates the calculated shift totals shown
above and the planners and repair co-ordinators can assign the daily
trade manpowers accordingly.
Sample graph loadings for major trades in
ship repairing
(It should be noted that these sample graphs are actual loadings that
were used by a certain major ship repair yard from figures compiled
from production feed back over a number of years. These graphs
were then used by the commercial division planners to predict the
required manpower resources for up to three months ahead.)
Planning charts 89
1 2 3 4 5 6 7 8 9 10
Shifts
180
160
140
120
100
80
60
40
20
0
Marine fitters: Man-hours/Time, shifts
Man-hours
Man-hours
90 Guide to Ship Repair Estimates (in Man-hours)
% Time
100
90
80
70
60
50
40
30
20
10
0
Hull blasting painting man-hours
% Work
0 10 20 30 40 50 60 70 80 90 100
●
●
●
●
●
●
●
●
●
●
●
% Time
100
90
80
70
60
50
40
30
20
10
0
Marine fitter man-hours
% Work 0
10 20 30 40 50 60 70 80 90 100
●
●
●
●
●
●
●
●
●
●
●
Planning charts 91
% Time
100
90
80
70
60
50
40
30
20
10
0
Marine steelworker
% Work
0 10 20 30 40 50 60 70 80 90 100
●
●
●
●
●
●
●
●
●
●
●
% Time
100
90
80
70
60
50
40
30
20
10
0
Marine pipefitter man-hours
% Work
0 10 20 30 40 50 60 70 80 90 100
●
●
●
●
●
●
●
●
●
●
●
92 Guide to Ship Repair Estimates (in Man-hours)
% Time
100
90
80
70
60
50
40
30
20
10
0
Marine welder/burner
% Work
0 10 20 30 40 50 60 70 80 90 100
●
●
●
●
●
●
●
●
●
●
●
% Time
100
90
80
70
60
50
40
30
20
10
0
Marine electrician man-hours
% Work 0
10 20 30 40 50 60 70 80 90 100
●
●
●
●
●
●
●
●
●
●
●
Index 93
Index
Air compressors, 60, 61
Air receivers, 61
Anchors and cables, 26
Auxiliary boiler, 67
Auxiliary steam turbines, 58
Ballast water tank cleaning, 84
Bearing survey, 45, 50
Berth preparation, 5
Bilge area hand cleaning, 84
Bilge water or slops handling,
83
Boilers, 67
Cables, anchors, 26
Cargo pump turbine, 58
Cargo pumps, 60
Chain lockers, 27
Compressors, air, 60, 61
Condenser, 54
Crankcase doors, 45, 46, 51
Crankshaft deflections, 45, 46,
51
Cylinder head, 43, 48
Cylinder liners, 44, 49
Diesel engines, 42, 47
Dock rent per day, 6
Dock services, 7
Docking and undocking, 6
Docking blocks, shifting, 5
Docking plugs, 22
Drydocking works, 5–28
Duplex pump, 64
Electric cable conduit, 82
Electric cable tray, 80
Electric cable, armoured, multicore,
77, 78
Electric cable, single core, 79
Electric cable, un-armoured,
multi-core, 75, 76
Electric cables, 75–79
Electric generators, 73
Electric motors, 71
Electric motors, crane, 72, 73
Electric motors, winch, 72, 73
Electric motors, windlass, 72,
73
Electrical insulation resistance
tests, 69
Electrical switchboard, 70
Electrical works, 69–82
Feed pump turbine, 59
Feed pumps, 59
Flexible coupling, 57
Four stroke auxiliary diesel
engines, 47
Four stroke main propulsion
diesel engines, 47
Fresh water tank cleaning, 84
Fuel oil tank cleaning, 84
Gear pump, 65
General works, 83–84
Gudgeon pin, 48
Heat exchanger, 55
Hollow fenders in half pipe, 25
Hull painting area formula, 12
Hull painting of names,
homeport, load lines, draft
marks, 10
Hull painting special notes, 11
Hull painting, 10
Hull preparation by degreasing,
8
Hull preparation by disc
preparation, 8
Hull preparation by dry blast, 8
Hull preparation by grit blast, 8
Hull preparation by grit sweep,
8
Hull preparation by hand
scraping, 8
Hull preparation by high
pressure jetwash, 8
Hull preparation by hose down
with fresh water, 8
Hull preparation by spot blast, 8
Hull preparation by vacuum dry
blast, 8
Hull preparation by water blast,
8
Hull preparation special notes, 9
Hull preparation, 8
Hull steel repairs, 29
Internal steel hand scraping, 84
Main condenser, 54
Main steam turbines, 57
Mechanical works, 41–67
Megger tests, electrical
insulation resistance, 69
Oil tanker cargo pump, 60
Pipe clamps, 38
Pipe spool pieces, 39
Pipe work renewals in copper,
37
Pipe work renewals in schedule
40 steel, 35–36
Pipe work renewals in schedule
80 steel, 35–36
94 Index
Pipe work, hot dip galvanising
after manufacture, 36
Pipeworks, 35–39
Planning works, 85–92
Propeller cleaning, in-situ, 16
Propeller removal, 14
Propeller repairs and balance
checking, 14,15
Propeller works, 14
Pumps, 62
Reciprocating pump, motor
driven, 64, 65
Reciprocating pump, steam
driven, 64,
Rudder clearances, 13
Rudder gland packing, 13
Rudder removal, 13
Rudder works, 13
Sea chests, 22
Sea grids, 22
Sea valves, 23
Simplex pump, 64
Sludge handling, 83
Staging, 28
Steam turbines, 58
Steel weight calculation method,
30–31
Steel repairs, 29
Steel works, special notes, 33
Steelworks, 29–33
Steering gear, 66
Stern gland patent seals, 19
Stern gland repacking, 19
Storm valves, 24
Tailshaft clearances, in-situ, 17
Tailshaft crack detection by
Magnaflux test, 19
Tailshaft patent seals, 19
Tailshaft removal externally, 18
Tailshaft removal internally, 18
Tailshaft works, 17–19
Tank cleaning, 84
Tank manhole cover removal, 84
Tank testing by filling with sea
water, 84
Tank testing by low pressure
compressed air, 84
Top overhaul, diesel engine, 43,
48
Turbines, steam, 58
Turbo alternator, 58
Two stroke main propulsion
diesel engines, 42
Valve, high pressure, 52
Valve, pipeline, 52
Valve, sea, 23
Water-tube boiler, 67
Zinc anode quantity calculation,
20–21
Zinc anodes, 20
Index 95
Tidak ada komentar:
Posting Komentar